  • PV source
    • Check the voltage and polarity for each parallel string of PV modules. The value will vary based upon the conditions but should be within an appropriate range given the conditions.
    • If voltages and polarities are correct, close (turn on) all overcurrent protection devices/disconnects between the PV source and the charge controller.
    • Has the charge controller registered the voltage from the PV source? If so, proceed with the process.