Perform a physical revision of the system as compared to the system design in the plans:
- Are all components the correct manufacturer and model? Are the power and voltage ratings correct?
- Is the system properly labeled?
- Are all system components connected to one another correctly?
- Is the grounding system built properly?
- Are all system connections made properly?
- Are all series and parallel connections performed correctly?
- Wiggle the wires for each connection to ensure that they are not loose.
- Are all wires the correct size?
- Are all wires protected and secured?