Translations:Commissioning/24/en

From Open Source Solar Project
Jump to navigation Jump to search
  • Power distribution
    • Check the voltage and polarity of any DC lighting circuits or DC circuits connected to the energy storage system. Is the voltage and polarity correct for the design?
    • If the voltage and polarity are correct, close (turn on) all overcurrent protection devices/disconnects between the DC power source and the loads.
    • Have the loads (lights and appliances) registered the voltage from the DC power source? If so, proceed with the process.
    • Check the voltage of all AC circuits connected to the inverter. Is the voltage correct for the design?
    • If the voltage is correct, close (turn on) all overcurrent protection devices/disconnects between the AC power source and the loads.
    • Have the loads registered the voltage from the AC power source? If so, proceed with the process.