  • Load: The make and model or type of load.
  • Quantity: The number of the particular load.
  • Watts: The power rating in watts for the load.
  • Total watts = Quantity × watts
  • Duty cycle = Rated or estimated duty cycle for the load. If the load has no duty cycle a value of 1 should be used. A load with a duty cycle of 20% would be inputted as .2
  • Surge factor = Rated or estimated surge factor for the load. Common values are between 3-5. If the load does not have a surge requirement a value of 0 should be used.
  • Surge watts = Total watts × Surge factor
  • Power factor = Rated or estimated power factor for the load.
  • Volt-amperes (VA) = Total watts ÷ Power factor
  • Hours per day: The maximum number of hours the load(s) will be operated per day. If the load has a duty cycle 24 hours should be used.
  • Days per week: The maximum number of days the load(s) will be operated per week.
  • Average daily AC watt-hours = Total watts × Duty cycle ÷ Inverter efficiency (Step 1) × Hours per day × Days per week ÷ 7 days