  • Check voltage at the overcurrent protection device/disconnect for the charge controller. Is the voltage and polarity correct for the design?
  • If voltage and polarity is correct, close (turn on) all overcurrent protection devices/disconnects between the energy storage system and charge controller.
  • Has the charge controller registered the voltage and turned on? If so, proceed with the process.