  • Perform a physical revision of the system as compared to the system design:
    • Are all components the correct manufacturer and model? Are the power and voltage ratings correct?
    • Is the system properly labeled?
    • Are all system components connected to one another correctly?
    • Is the grounding system built properly?
    • Are all system connections made properly?
    • Are all series and parallel connections performed correctly?
    • Wiggle the wires for each connection to ensure that they are not loose.
    • Are all wires the correct size?
    • Are all wires protected and secured?