Perform a physical revision of the system as compared to the system design in the plans:
(Importing a new version from external source) |
(Importing a new version from external source) |
||
Line 1: | Line 1: | ||
− | <li>Perform a physical revision of the system as compared to the system design:<li/> | + | <li>Perform a physical revision of the system as compared to the system design in the plans:<li/> |
:*Are all components the correct manufacturer and model? Are the power and voltage ratings correct? | :*Are all components the correct manufacturer and model? Are the power and voltage ratings correct? | ||
:*Is the system properly labeled? | :*Is the system properly labeled? |
Latest revision as of 15:13, 9 March 2021
- Are all components the correct manufacturer and model? Are the power and voltage ratings correct?
- Is the system properly labeled?
- Are all system components connected to one another correctly?
- Is the grounding system built properly?
- Are all system connections made properly?
- Are all series and parallel connections performed correctly?
- Wiggle the wires for each connection to ensure that they are not loose.
- Are all wires the correct size?
- Are all wires protected and secured?