Difference between revisions of "Translations:Commissioning/16/en"

From Open Source Solar Project
Jump to navigation Jump to search
(Importing a new version from external source)
 
(Importing a new version from external source)
 
Line 1: Line 1:
 
:*Check voltage at the overcurrent protection device/disconnect for the charge controller. Is the voltage and polarity correct for the design?  
 
:*Check voltage at the overcurrent protection device/disconnect for the charge controller. Is the voltage and polarity correct for the design?  
:*If voltage and polarity is correct, close (turn on) all overcurrent protection devices/disconnects between the battery bank and charge controller.
+
:*If voltage and polarity is correct, close (turn on) all overcurrent protection devices/disconnects between the energy storage system and charge controller.
 
:*Has the charge controller registered the voltage and turned on? If so, proceed with the process.
 
:*Has the charge controller registered the voltage and turned on? If so, proceed with the process.

Latest revision as of 15:13, 9 March 2021

Information about message (contribute)
This message has no documentation. If you know where or how this message is used, you can help other translators by adding documentation to this message.
Message definition (Commissioning)
:*Check voltage at the overcurrent protection device/disconnect for the charge controller. Is the voltage and polarity correct for the design? 
:*If voltage and polarity is correct, close (turn on) all overcurrent protection devices/disconnects between the energy storage system and charge controller.
:*Has the charge controller registered the voltage and turned on? If so, proceed with the process.
Translation:*Check voltage at the overcurrent protection device/disconnect for the charge controller. Is the voltage and polarity correct for the design? 
:*If voltage and polarity is correct, close (turn on) all overcurrent protection devices/disconnects between the energy storage system and charge controller.
:*Has the charge controller registered the voltage and turned on? If so, proceed with the process.
  • Check voltage at the overcurrent protection device/disconnect for the charge controller. Is the voltage and polarity correct for the design?
  • If voltage and polarity is correct, close (turn on) all overcurrent protection devices/disconnects between the energy storage system and charge controller.
  • Has the charge controller registered the voltage and turned on? If so, proceed with the process.